BUILDING INFORMATION
The interior work that is going on in House K during the coming week is carpeting, painting, assembly of doors and partitions, ceiling work, interior walls and installation work for electricity, etc. and ventilation. Exterior work that will take place next week is ground work down towards the bus street and the south-west long side with stairs, demolition of scaffolding around the entire building and dismantling of the construction lift on the outside.
Installation work, painting and the connection to Aula Nordica continue on the link.
On the annex, work continues with the connection to the House of Natural Sciences, which entails drilling and other construction work. Interior work as well as work with roofs and walls on skywalks will continue next week as well.
PLANNING FOR COMING WEEKS
Please note that the activities below may cause some disturbance to nearby businesses.
Weeks 39–40
- House K: Interior walls, painting, carpeting, technical installations, false ceilings, assembly of doors and partitions, earthwork in connection with the bus street and the south-west long side with stairs, demolition of scaffolding around the entire building and dismantling of construction lift on the outside.
- The link: Connection to Aula Nordica, painting and installation work.
- Annex: Roof/walls and internal work on skywalks, connection to the House of Natural Sciences, which entails drilling and other construction work.