CONSTRUCTION INFORMATION
Construction and work from last week will continue on site next week and then slow down in relation to the holiday period from v29-v32. During these weeks there will only be a few activities, such as electrical installation work.
Building K: Technical installations, work on internal walls, painting, carpeting, facade, roof work with wall coverings, suspended ceilings and ground work at Bus Street. Link: Connection to Aula Nordica, walls and roof. Annex: Party assembly and roof/walls for skywalks. District heating center: technical installations and interior work.
Access to Johan buresväg via Gösta Skoglundsväg is still closed until v27. This is due to excavation work in connection with the new district heating center.
PLAN FOR UPCOMING WEEKS
Please note that the activities below may cause some disturbance.
Week 27-28.
- Building K: Technical installations Interior walls, painting, laying carpeting, roofing work with wall coverings, sheet metal, facade and suspended ceiling work. Ground works in connection with the bus street.
- Link: Connection to Aula Nordica, walls and roof work.
- Annex: Part assembly, roof/walls on skywalk.
- District heating plant: technical installations and internal works.ork.