BUILDING INFORMATION
The interior work that is going on in House K during the coming week is carpeting, painting, assembly of doors and partitions, suspended ceiling work, installation work for electricity, etc. and ventilation, supplementary work inside and final cleaning. External works in progress are earthwork at the east gable and south-west long side with stairs.
Installation and facade work continues on the link.
On the annex, work continues with the connection to the House of Natural Sciences, interior work and carpeting on skywalks
PLANNING FOR COMING WEEKS
Please note that the activities below may cause some disturbance to nearby businesses.
Week 47–48
- House K: painting, carpeting, technical installations, false ceiling, door and partition assembly, supplementary work inside, final cleaning, earthworks at the eastern gable and south-west long side with stairs.
- The link: Installation work and facade work.
- Annex: Interior work and carpeting on skywalks and connection to the House of Natural Sciences.