Update 12/18
Dehumidification of floor joists is complete and work to restore the premises has begun. Currently, they are in full swing with installing new insulation and plasterboard. Painting work goes on in parallel as the boards come up.
The classrooms are prioritized according to the wishes of the University. The time when it might be ready is difficult to estimate, but a qualified guess is that the classrooms will be ready before the middle of January, assuming there are no problems with deliveries.
Sincerely
Joakim Ekholm
The Forum House. A coffee machine in the Staff Pantry (south side) started leaking early in the morning on Sunday 1/10. Damage engineering has been out and made moisture measurements to be able to make an assessment of the extent.
A number of offices adjacent to the Pantryt and classrooms are closed until further notice. At present, it is difficult to say how long. this will take. We need to open up walls and floor mats to then dry concrete and replace moisture-damaged material. The work starts today.
This text has been automatically translated, and some inaccuracies may be present.