Work will be carried out with waterproofing, sheet metal and scaffolding work on the A building, LTH starting V32, on Monday, August 7, 2023.
BUILDING INFORMATION WEEK 32-37, 2023
In order to carry out the rearrangement of the roof, it is required that a scaffolding be built on the eastern facade. The scaffolding that is being built consists of a footbridge fall up on the roof with spiers down on the facade. An external stair tower will be used for passenger transport up to the roof. The stair tower is planned to be placed in the courtyard.
- It can smell when cardboard is laid on the roof, the smell can possibly get in via air intake or window.
- ATTENTION! There will be cranes and trucks around the building during construction.
- Work takes place between 07.00 and 16.00
Week 32-37, 2023
V32 The scaffolding and stair tower are mounted on the roof and the eastern facade.
V33-36 Roofing work
V37 Dismantling stand
For questions, contact project manager Mikael Renstrand Akademiska Hus 070-3691326