Sunday 18 October, 2026
Universum - Info about renovation
The renovation of Universum has begun. More information can be found in the attached link.Information is updated continuously.
Campus
Sunday 18 October, 2026
Universum - Info about renovation
The renovation of Universum has begun. More information can be found in the attached link.Information is updated continuously.
Friday 16 October, 2026
Roofing work at the Social Sciences Building
We have now received the delivery of the new roof unit and have carried out preparatory work this week. Next week, we will begin on Tuesday by dismantling the old roof unit and performing preparatory tasks, followed by the installation of the new unit on Wednesday. Afterward, interior work will take place to restore the offices and the group room. The work is weather-dependent; should the weather deteriorate, we will postpone the installation.
Friday 16 October, 2026
Skywalk closed
The skywalk between KBC and NAT will be closed for floor maintenance from Wednesday, October 21, at 08:00, until Thursday, October 22, at 16:00.
Friday 16 October, 2026
Exam Hall, Floor 4 – Fire Alarm Test, Wednesday 21/10
Work on the examination hall is nearing completion. Next week, we will be carrying out adjustments and finalizing installations ahead of the upcoming inspection in week 44. On Wednesday, October 21, at 07:30, we will conduct a test of the fire alarm system on floor 4.
Thursday 15 October, 2026
KBC Physiology building construction project time schedule
Hi!See the attached time schedule for an overview of the construction at south west KBC Physiology building and the amount of expected disruption during the different phases of the project. If you have any questions please feel free to contact me at jon.soderqvist@akademiskahus.se or 070 697 62 19.Regards Jon
Monday 12 October, 2026
Construction project at KBC-Fysiologihuset building E week 42
Hi!Demolition continues at KBC-Fysiologihuset building E. Please see the attached information. If you have any questions please contact Jon Söderqvist, project manager at Akademiska Hus. jon.soderqvist@akademiskahus.se 070 697 62 19.Regards Jon
Monday 12 October, 2026
Noise from construction site at Linnaeus väg
Hi!For the upcomming 2-3 weeks there will be a large air compressor at the construction site by Linnaeus väg. It makes quite a bit of noise that will be noticed in the eastern part of the Biology building. The contractor will palce the air compressor as far to the south as possible in order to maintain distance to the Biology building. RegardsJon
Friday 9 October, 2026
Project information V.42-v.43
Friday 9 October, 2026
Roofing work on the Social Sciences Building
Next week, we will complete the final preparatory work so that we can install the new roof element the following week—that is, week 43. Since the weather determines exactly when we can install the new roof—as it must not rain while we are opening up the roof and installing the new section—I will get back to you with more information at the end of next week.
Monday 21 September, 2026
LED lighting at the Natural Sciences Building
To create more efficient lighting, we are upgrading and switching to LED. In accordance with the new EU directives, which prohibit the import and manufacture of certain fluorescent and halogen lamps, we are taking a step towards a more energy-efficient and sustainable future by switching to modern LED alternatives in the Science Building.The work has now begun and will continue throughout the spring and into the summer of 2027. The lighting replacement has started on floor 5 and will then continue downwards in the property. There will be some noise impact, but it is expected to be relatively short-lived.There will also be some physical impact when the work is taking place in the corridor and office/lab. This is continuously coordinated with those responsible at Umeå University.If you have any questions, please contact Akademiska Hus project manager, Markus.hertzberg@akademiskahus.se