Campus
Umeå
Disturbances & Info
Posts
Monday 15 June, 2026
Project information V25-V26
Monday 15 June, 2026
Fencing construction area
From Wednesday, June 17, the construction area will be fenced off as shown in the picture.
Friday 12 June, 2026
Continued construction at KBC Odlinghuset
Work will continue for the next two weeks high and low.At the bottom of level 2 we finally continue to reinforce the foundation after a little problems after we were surprised by several sewer and stormwater pipes that were not as expected. It will be completed during the next week, (week 25).We still have work to do on floor 3. The pillars closest to the climate chambers need be made in two parts and joined together in place. This is done during week 25.A plumber is investigating where we can turn off heating and gas to place pillars closest exterior wall to the east on both floors 3 and 4. Any disruptions in gas are coordinated with Jan Karlsson on Fys bot and communicated that way out to the affected personnel. We count with shorter stops.Pouring of columns on floors 3 and 4 is carried out in week 26. This means that we cast with a small amount of easy-flowing concrete during each pillar. Then cleaning is carried out and restoration of surfaces.The steel assembly on floor 5 will be completed at the beginning of week 25. Regarding the steel assembly, I was incorrectly informed that it would happen without impact drilling but I later understood that this was not the case and that it probably has sounded quite a lot in Odlingshuset when steel beams have been attached to the concrete structure. I apologize for this misunderstanding.After Midsummer week 26 we start assembling roof sheet and it is also ongoing during week 27. The installation of the sheet metal will rattle but the indoor disturbance will be quite limited.Week 28-31 the site will be closed for summer during week 28-31. We from Academiska Hus and the building team wishes everyone a nice summer!
Friday 12 June, 2026
Planned power outage
Tuesday 23/6 at 2-3 pm there will be a planned power outage
Monday 8 June, 2026
CLOSED STAIRCASE
From Monday 15/6- 2026, stairwell D2 01 07 will be closed on all floors due to renovation.Provisional entrance to the library is via the door next to the main entrance to Lindell.Please respect the closure and choose stairwell D2 01 27 instead.
Thursday 4 June, 2026
Floor carpet maintenance levels 3-4
Maintenance of floor carpet on floors 3-4 will be carried out during week 25, Monday 15/6.
Monday 1 June, 2026
Waterworks outside Universum
In connection with the reconstruction of Universum, underground water management will be carried out. The start of these works is during week 24.Monday, June 8: Road Rental establishes heavy protection and signs according to the TA plan for excavation area 1.Tuesday, June 9: We will take down birch trees that are too close to the starting well.Wednesday, June 10: Establish excavator, Stakeout Umeå Energi and geomatics (fiber, telephone) for cable placement,
Monday 1 June, 2026
Waterworks outside Universum
In connection with the reconstruction of Universum, underground water management will be carried out. The start of these works is during week 24.Monday, June 8: Road Rental establishes heavy protection and signs according to the TA plan for excavation area 1.Tuesday, June 9: We will take down birch trees that are too close to the starting well.Wednesday, June 10: Establish excavator, Stakeout Umeå Energy and geomatics (fiber, telephone) for cable placement,
Monday 1 June, 2026
Planned power outage University Library
Switching SwitchgearOn Wednesday, July 1st, 26th, the University Library and Lindellhallen will be without power for approximately 8 hours starting at 7:00 a.m. This is to connect a new electrical supply.We thank you for your consideration.
Monday 1 June, 2026
Project information V.23-24